The project involved the replacement of both cooling towers as well as the roof in the cooling tower mechanical roof. The replacement of the chilled water pumps and condenser water pumps as well as modifying the necessary piping in order to optimize the system was included in the scope of work. The work had to be accomplished with minimal disruption to the building occupants and courthouses in the building. The project was carried out in several phases and the schedule had to be specific to seasonal changes.

Heating
Ventilation
Plumbing

The main components of the project’s mechanical systems are :

  • Replacement of the two cooling towers in separate phases;
  • The replacement of the existing pumps with new Armstrong pumps, also conducted in separate phases;
  • Modifications to the piping arrangement also conducted in phases;
  • The removal and transport of the old cooling towers;
  • Coordination for the transport of the new towers
  • Installation and commissioning of the new Marley cooling towers.

We provided the following services :

  • The piping work for the cooling towers;
  • The chilled water piping modifications;
  • Plumbing;
  • Thermal insulation (subcontracted).

Privacy policy

By agreeing to share certain navigation information with us, you are helping us to improve and offer you an optimal browsing experience. Thank you for your support! Privacy policy

Activate the categories you want to share, thanks for your help! Privacy policy

  • None for the moment
  • None for the moment
  • None for the moment